B
BCAL ENERGY
Start a Conversation
Bcal Energy White Paper Series · No. 052

Sizing for a Load That Has Not Arrived Yet

Growth forecasts are the least reliable input in an energy model and the most expensive one to get wrong in either direction. How to size service and on-site power against a load you cannot yet measure, what oversizing now costs under current utility terms, and why part-load behavior changes the technology ranking.

Every energy decision rests on a load. When the load already exists, it can be measured, and the argument moves on to technology and cost. When the load has not arrived yet, the most consequential number in the entire study is a forecast, and the study's honesty depends almost entirely on how that forecast is handled.

Section 01The forecast is the weakest input in the model

Energy models present all their inputs in the same typeface. Fuel price, equipment cost, maintenance intervals, and projected load appear as columns of equal weight. They are not of equal weight. Most of the inputs describe things that already exist and can be quoted. The load forecast describes a decision that has not been made yet, by people who may not have made it, about a business that may look different when the time comes.

The scale of that uncertainty is not a matter of opinion. It is visible in the most scrutinized load forecast on the continent. In its 2025 Long-Term Reliability Assessment, released January 29, 2026, the North American Electric Reliability Corporation projected ten-year summer peak demand growth of 224 gigawatts, more than a 69 percent increase over the forecast published in the prior year's assessment for substantially the same horizon. Winter peak growth was projected at 246 gigawatts. NERC attributes most of the increase to new data centers and the digital economy.1

69%
Increase in NERC's ten-year summer peak demand growth forecast in a single assessment cycle, 2024 to 2025 assessment1
6.7–12%
Range for data centers' share of total U.S. electricity by 2028, stated as a range by the U.S. Department of Energy and Berkeley Lab2

The second figure makes the same point from the other direction. The Department of Energy's December 2024 report, prepared by Lawrence Berkeley National Laboratory, put data center consumption at roughly 4.4 percent of U.S. electricity in 2023, or about 176 terawatt-hours, and projected a 2028 range of approximately 6.7 to 12 percent, or 325 to 580 terawatt-hours.2 The authors did not publish a point estimate. They published a spread of roughly 255 terawatt-hours because that spread is the honest answer.

Institutions with far more data than any single site, and no commercial interest in the outcome, decline to give a single number four years out. An owner who has been handed one for their own site, without a range and without named drivers, is holding a weaker document than they think.

This is not an argument for paralysis. Capital decisions get made under uncertainty every day in every industry. It is an argument for treating the forecast as what it is: the input most likely to be wrong, and therefore the input the entire design should be stress-tested against first.

A forecast is not a fact about the future. It is a statement about what someone intends today, and intentions are revised.

Section 02Requested capacity and arriving capacity are different quantities

The gap between what is asked for and what gets built is now visible in utility disclosures. Pacific Gas and Electric Company reported in its second-quarter 2026 results, released July 23, 2026, an overall data center pipeline in its service area of more than 12 gigawatts.3 Three months earlier, in first-quarter results released April 23, 2026, the company reported approximately 4.6 gigawatts of customer data center projects in final engineering.4

Those two figures come from different quarters and describe different stages, so they do not produce a clean attrition rate and should not be presented as one. What they do establish is that the utility itself distinguishes between a pipeline and a project in final engineering, and that the two numbers are of different magnitudes. Any capacity figure quoted in a study should carry the same distinction: which stage is this, and who has committed what.

The practical lesson for an individual owner is narrower and more useful. If the aggregate pipeline in your territory is substantially larger than the volume of work that reaches engineering, then two things follow at once. Your own request is competing against a queue that is partly speculative, which argues for moving early. And your own forecast is subject to the same discount that everyone else's is, which argues against sizing to the optimistic case.

Section 03Reserved capacity is no longer free

For most of the last half century, asking a utility for more capacity than you ended up using was close to costless. That is changing, and the change is being written into tariffs.

The clearest published example is the data center tariff approved by the Public Utilities Commission of Ohio in Case No. 24-508-EL-ATA. The commission adopted a stipulation on July 9, 2025, and the compliance tariff took effect July 23, 2025. Its terms are worth reading closely by anyone in any state who is about to request capacity for a load that does not yet exist. Under the published schedule, facilities requesting 25,000 kilowatts or more enter a mandatory load study process, with load study fees stated at $10,000 to $100,000 depending on capacity requested. A load ramp period of up to four years applies, with graduated minimum capacity obligations of 50 percent in year one, 65 percent in year two, 80 percent in year three, and 90 percent in year four. After the ramp, monthly billing demand is set at no less than the greater of 85 percent of the customer's highest previously established monthly billing demand during the past eleven months or tiered percentages based on contract capacity. The initial term equals the ramp period plus eight years, up to twelve years in total. A customer may exit after the fifth year following the ramp by paying minimum charges for thirty-six months after notice of termination. Customers without an A-minus or A3 credit rating and substantial cash reserves must post a guarantee or collateral equal to 50 percent of the total minimum charges for the full term.5

Read that as a price list rather than a rule book. It is one utility's published answer to the question this paper asks. The answer is that a request for capacity you might not use will be converted into a multi-year minimum payment obligation, secured by collateral, with a defined cost to walk away.

California is moving on the same axis by a different route. On July 24, 2025, the California Public Utilities Commission approved interim implementation of PG&E's Electric Rule 30 for transmission-level retail service, conditioned on applicants paying for necessary transmission infrastructure work up front, with the terms and cost allocation of any refunds left to a future decision. The commission described the framework as protecting ratepayers from potential risks associated with serving large new loads.6 The mechanism differs from Ohio's. The direction of travel is the same: the party requesting capacity carries more of the risk that the capacity is never used.

An owner sizing a service request in 2026 should therefore assume that the number written on the application is closer to a commitment than it used to be, and should size it the way a commitment is sized.

Section 04The two failure modes, priced against each other

Sizing errors are not symmetrical, and the asymmetry runs in different directions at different sites. The purpose of the table below is to force both columns into the same document, because most sizing conversations only argue one of them.

DimensionOversized for the load that arrivesUndersized for the load that arrives
CapitalCapital is spent and sits idle. Under current federal law the investment tax credit for qualifying energy property is 30 percent, so a portion of an over-spend is recovered and the majority is not.7Capital is deferred, which preserves optionality, but the second tranche is bought at a later date's prices and a later date's lead times.
Utility termsMinimum billing demand, ratchets, contract minimums, collateral, and termination charges apply to capacity reserved rather than capacity used.5An expansion request re-enters the process at the back of a queue that has grown since the first application.
Operating efficiencyEquipment runs below its design point, where efficiency penalties vary widely by technology (Section 05).Equipment runs near or above its design point, which is efficient but leaves no headroom for the load's own peaks.
ScheduleNo schedule penalty. The capacity is there early, which for some owners is the entire point.The binding risk. If the deadline that motivated the project is missed, every other economy is irrelevant.
ReversibilityHard to reverse. Installed capacity, signed terms, and posted collateral do not unwind cheaply.Reversible but slow. Adding capacity is usually possible; adding it quickly usually is not.
Where it hurts mostSites whose growth is genuinely uncertain, or contingent on a decision outside the owner's control.Sites with a dated, external deadline: a lease, a permit condition, a production commitment, a tenant.

The table is not a recommendation. It is the shape of the trade. Which column dominates depends on one question that a study can actually answer: is the deadline the binding constraint, or is the capital the binding constraint? Sites where the deadline binds should accept some oversizing risk. Sites where capital binds, and where the growth is contingent on a decision that has not been made, should not.

Section 05Part load is where the technology ranking changes

If a site's load will sit well below design capacity for the first several years, part-load behavior stops being a specification footnote and becomes a first-order selection criterion. It is one of the few places where the honest ranking of technologies at partial load differs materially from the ranking at full load.

The U.S. Environmental Protection Agency's Catalog of CHP Technologies provides manufacturer-neutral figures. Gas turbines typically show efficiency decreases on the order of 15 to 25 percent at half load. Spark-ignition gas engines compare favorably, with decreases on the order of 8 to 10 percent at 50 percent load, and compression-ignition engines show still better part-load characteristics.8 Fuel cells have good part-load performance; at 50 percent of full load the efficiency of a fuel cell typically declines less than 2 percent relative to its full-load value.9

Those numbers do not decide anything by themselves, and a study that stops there is doing the same selective work it was hired to prevent. The honest version of each case:

The point is not that one row wins. It is that a load which will spend years at partial output ranks these rows differently than a load that arrives at full size on day one, and a study that never states which case it is analyzing has not analyzed either.

Section 06Modularity is an option, and options have a price

The standard answer to an uncertain load is modularity: install less now, add units as the load appears. It is usually the right instinct and it is never free.

What modularity buys is real. Capital is staged against demonstrated load rather than forecast load. Turndown improves, because a plant of several units can shut units off rather than run one large machine at low output. Redundancy arrives as a side effect. And the decision to expand gets made later, with better information.

What modularity costs is equally real and is routinely left out of the comparison. Capital cost per unit of capacity is generally higher for several small units than for one large one. Maintenance events multiply with unit count. Footprint grows, which matters where land or roof area is already tight. Each permitted unit is a unit the air district evaluates, and in a constrained district the count itself can become a permitting variable. Balance-of-plant, controls, and interconnection work must be designed once for the full build-out or redone at each phase, and the first of those choices is itself a sizing decision made under the same uncertainty.

The disciplined treatment is to price modularity as what it is: an option on the load forecast. An option is worth buying when the underlying uncertainty is large and the cost of being wrong is high. It is not worth buying when the load is contractually committed and dated, because then the owner is paying an uncertainty premium on a certainty.

Section 07What to fix before capital moves

The following can be worked through with a finance lead and a facilities lead in an afternoon. Every item is a question about the load rather than about equipment, which is the correct order.

  1. State the load as stages with dates, not as an endpoint."We will reach X by 2030" is not a sizing input. A dated schedule of what is expected to be running in each year is. The design is then tested against the schedule, not against the endpoint.
  2. Separate contracted load from expected load from aspirational load.Three different confidence levels routinely arrive in one spreadsheet cell. Split them, label each, and note who would have to decide what for the second and third tiers to become real.
  3. Get the ramp and minimum-demand terms in writing before you size to them.Ramp schedules, ratchets, minimum billing demand, term length, exit charges, and collateral are the actual cost of reserved capacity. A verbal indication of flexibility is not a term.
  4. Model year two, not just year ten.Most designs are validated at full build-out. The years that determine whether the project survives its own business case are the early ones, at partial load, paying minimums.
  5. Ask what the recommendation would be at half the forecast.If the answer is the same design, the forecast was not load-bearing and the study can proceed. If the answer is a different design, the forecast just became the most important number in the room, and it deserves a range.
  6. Price the part-load case explicitly for each candidate.Full-load efficiency comparisons are the wrong test for a load that has not arrived. Ask for efficiency and maintenance treatment at the output the site will actually see in its early years.
  7. Write down the trigger that reopens the decision.A named, observable event: a signed lease, a permit issued, an executed interconnection agreement, a production line ordered. Without a trigger, a phased plan quietly becomes a single-phase plan.

Section 08Sizing is a decision about uncertainty

The failure this paper describes is rarely arithmetic. Nobody multiplies wrong. The failure is that a forecast enters the model with the same authority as a quoted equipment price, travels through the analysis unlabeled, and emerges at the other end as a capacity number on a signed application with a twelve-year term behind it.

The correction is not more precision in the forecast. Precision is not available, which is why the institutions with the most data publish ranges. The correction is to build the decision so that it survives being wrong: staged where staging is cheap, committed where the deadline binds, tested at half the forecast, and reopened on a named trigger rather than on a feeling.

Our conviction is that green energy is only sustainable if it is profitable, and profitability under uncertainty comes from designs that do not require the forecast to be right. All the paths, sourced numbers, dated facts, one decision, tested against the load that actually shows up.

Sources

  1. North American Electric Reliability Corporation, 2025 Long-Term Reliability Assessment, released January 29, 2026. nerc.com. Accessed August 11, 2026.
  2. U.S. Department of Energy, "DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers," December 20, 2024, reporting Lawrence Berkeley National Laboratory, 2024 United States Data Center Energy Usage Report. energy.gov. Accessed August 11, 2026.
  3. PG&E Corporation, "PG&E Corporation Reports Second Quarter 2026 Results," July 23, 2026. investor.pgecorp.com. Accessed August 11, 2026.
  4. PG&E Corporation, "PG&E Corporation Reports First Quarter 2026 Results," April 23, 2026. investor.pgecorp.com. Accessed August 11, 2026.
  5. AEP Ohio, Data Center Tariff (Schedule DCT) summary of terms; adopted by the Public Utilities Commission of Ohio in Case No. 24-508-EL-ATA (stipulation approved July 9, 2025; compliance tariff effective July 23, 2025). aepohio.com. Accessed August 11, 2026.
  6. California Public Utilities Commission, "CPUC Streamlines Electric Grid Connections for High-Energy Users Like Data Centers and EV Chargers," July 24, 2025 (interim implementation of PG&E Electric Rule 30). cpuc.ca.gov. Accessed August 11, 2026.
  7. 26 U.S.C. §48 (investment tax credit for energy property; statutory rate for qualifying property, as amended). Statutory values as of August 2026; bonus adders exist in statute but must be individually qualified rather than assumed. Confirm current status with qualified tax counsel.
  8. U.S. Environmental Protection Agency, Catalog of CHP Technologies, Section 2: Technology Characterization — Reciprocating Internal Combustion Engines (part-load efficiency comparison, gas turbines and gas engines). epa.gov. Accessed August 11, 2026.
  9. U.S. Department of Energy Better Buildings Solution Center, "Combined Heat and Power Technology: Fuel Cells," drawn from EPA, Catalog of CHP Technologies, Section 6 (fuel cell part-load performance). energy.gov. Accessed August 11, 2026.
The series

One paper. Every day.

The Bcal Energy White Paper Series covers the decisions, technologies, and market evidence behind time-to-power. New research publishes continuously in the library.

Browse all papers
The study

Run this test on your own site.

The Power Readiness Study is our fixed-fee written analysis of every credible path to power for one specific site: $25,000, technology-neutral by design, sold with no equipment margin behind it. A free 20-minute conversation comes first.

info@bcalenergy.com

About Bcal Energy. Bcal Energy is an independent, founder-led California firm. We prepare technology-neutral power readiness studies for organizations facing time-to-power decisions, on the owner's side of the table. We sell the decision, not equipment. Author: Bharath Ramanidharan, Founder. Contact: info@bcalenergy.com.

Disclaimer. This paper is general information, not engineering, legal, tax, or investment advice, and not an offer of services on any specific terms. Figures described as illustrative are estimates. Statutory, tariff, and program references are current as of the publication date only; confirm status with qualified counsel and advisors before acting. Bcal Energy provides no guarantee of savings, output, performance, or timelines. © 2026 Bcal Energy.